Advancing strategically significant critical minerals assets through disciplined development.
1 Aug 2025
Project Kickoff & Regulatory Mobilization
Formal launch of the airborne MobileMT survey and transition into operational mobilization.
  • Civil Aviation approvals confirmed
  • Bureau Veritas inspection framework initiated
  • Customs and temporary import permits processed
  • Jet A1 logistics structured
  • Health, Safety and Environmental systems activated
  • Independent QA/QC consultants (Minrom and DMT) formally engaged
Milestone, Structured transition from planning to operational mobilization.
Mid Aug 2025
Compliance & Operational Readiness
Regulatory and administrative readiness completed ahead of full field operations.
  • Helicopter temporary admission secured in DRC
  • Airborne equipment customs clearance completed
  • Work permits and visas processed
  • Emergency response procedures implemented
  • Community engagement initiated
Milestone, Full regulatory and administrative readiness achieved.
Late Aug 2025
Independent QA/QC Framework Embedded
Dual independent technical oversight integrated into daily operations and reporting.
  • Minrom and DMT appointed for daily QA/QC oversight
  • Mutual cross verification procedures established
  • Joint sign off protocol agreed for final survey reporting
Milestone, Dual independent technical oversight formally integrated.
Early Sep 2025
Mobilization to Manono Site
Field operations deployed, infrastructure established, secure data transmission enabled.
  • Helicopter and airborne “bird” assembled
  • Base stations installed and calibrated
  • Starlink deployed for daily data transmission
  • Secure fuel storage and 24 hour aircraft guarding implemented
  • Police escorts for base station visits established
Milestone, Field operations fully mobilized.
Late Sep 2025
Test Flights & Survey Activation
Survey moved from preparation to active acquisition with structured QA/QC cycles.
  • Jet A1 fuel delivered
  • Initial test flights successfully conducted
  • Daily QA/QC review cycle initiated
  • Secure data upload protocols implemented
Milestone, Survey transitioned to active data acquisition.
Early Oct 2025
Full Production Phase
Stable, high efficiency production achieved with strong data quality and HSE performance.
  • Two sorties per day implemented
  • Average 250 km flown per day
  • Peak daily coverage exceeded 400 km
  • Data quality confirmed by DMT and Minrom geophysicists
  • Zero major HSE incidents recorded
Milestone, Stable, high efficiency survey production achieved.
Mid Oct 2025
Accelerated Progress & Schedule Recovery
Operational performance improved and earlier delays were recovered while maintaining quality controls.
  • Improved sortie performance reduced earlier delays
  • Conservative completion estimate set for 26 Oct 2025
  • Continuous Jet A1 monitoring and contingency planning
  • Daily technical reporting validated
Milestone, Operational efficiency optimized and quality standards maintained.
30 Oct 2025
Completion of Manono Airborne Survey
Full MobileMT survey line acquisition completed and archived under controlled protocols.
  • QA/QC validation cycles finalized
  • Data securely archived and distributed under controlled protocols
  • Transition to interpretation and geological integration initiated
Milestone, Successful completion of the 2025 airborne campaign.
31 Oct 2025
Extension & Controlled Demobilization
Orderly close out and secure relocation with reinforced medical and emergency protocols.
  • One day extension survey at Fungurume (Kalongo site)
  • Secure relocation of helicopter and equipment
  • Medical contingency and evacuation protocols reinforced
  • Final HSE and logistical close out planning initiated
Milestone, Campaign close out and transition to the next technical phase.
26 Feb 2026
Final Processed Dataset Received
Final processed and quality controlled dataset received, supporting geological modelling and drill targeting.
  • High resolution resistivity imaging across targeted structural corridors
  • Enhanced delineation of pegmatite hosting zones
  • Improved subsurface structural clarity to support drill targeting
  • Robust dataset suitable for integration into geological modelling
Milestone, Proceeding to interpretation and integration into updated models and exploration planning.
Final Validated Results Announced
Formal confirmation of validated MobileMT results and transition into interpretation and future program planning.